Project Update: Grubbs Volvo
Nearing completion on this beautiful Volvo dealership in Grapevine. Thanks to our team and our trade partners – terrific work!
Nearing completion on this beautiful Volvo dealership in Grapevine. Thanks to our team and our trade partners – terrific work!
Here’s the latest on Grubbs Volvo in Grapevine. Our team and our trade partners are currently … Finishing up the carwash Installing curtainwall and storefront frames at the exterior of building Painting throughout the building Installing ceiling grid and continuing with MEP overhead work Thank you for your hard work!
Our work continues at Grubbs Volvo in Grapevine. Electrical and plumbing rough-ins are ongoing. Ductwork is being installed throughout the dealership. Stucco installation is taking place and exposed columns and beams in the showroom are being painted. Thank you to our team and trade partners for their hard work!
A quick look at what’s happening at Grubbs Volvo in Grapevine … Exterior framing at the showroom and service drive continues Completed decking installation at the shop, and started installing steel supports for RTU screens Prepped for a 600-yard concrete pour Electrical rough-in started at the main building Plumbing rough-in is ongoing throughout Our thanks …
We’re hard at work on Grubbs Volvo in Grapevine … We’re erecting steel at the main building and plumbing rough-in is ongoing Electrical undergound is continuing throughout the site Rebar has been set in preparation to pour the Mezzanine slab Sidewalks have been completed along Texan Trail Grading is ongoing for the remaining paving Thank …
Since the beginning of the month, Fort Construction and our trade partners have completed two paving pours at Grubbs Volvo in Grapevine. We began erecting CMU at the car wash and continued underground electrical and plumbing. The building pad is prepped to be poured, and we’ll continue paving the rest of the site throughout the …
Construction on Grubbs Acura is moving along nicely with the project approximately 40-percent complete. The CMU installation is complete, almost all paving is poured, and 75-percent of the steel is erected. MEP rough-in and exterior framing will start this week. When all is said and done, this will be a 57,000 SF two-story car …
We are pleased with the progress on the new Audi dealership in Grapevine. So pleased, we asked Bartley’s BBQ to stop by and provide lunch while we offered tours through the facility. When all is said and done, the 62,000 SF facility will host a number of unique features. Here’s a few of them: Audi …
Fort Construction is continuing work on the Ryder Facility in Grapevine. The project includes three buildings as well as site utilities and the replacement of all asphalt paving with new concrete paving. We are working to renovate their existing truck maintenance facility – approximately 2900 SF – including an interior mezzanine. In addition to the …
Grubbs Infiniti, located at Highway 121 and Texan Trail in Grapevine, began operating in March 2015. Since then, according to George Grubbs III, they have experienced an amazing amount of growth in sales and service. Here’s what Mr. Grubbs had to share: “The new location was obviously a good decision. From the day we opened …
Have you ever heard an Academy Award nominee say, it was an honor just to be nominated? We know how they feel. We recently attended an awards ceremony for Topping Out, an industry award that honors a project’s entire construction team and their ability to work together toward a successful completion. The Grubbs Infiniti Dealership …
Fort Construction is proud to partner with Group 1 Automotive on a brand new Audi Dealership in Grapevine. The location will be on the south side of Highway 121, prior to the Texan Trail exit. Ground breaking for the 62,420 S.F. dealership is slated for late December/early January, with a completion date approximately ten months …