Overhead view of Grubbs Volvo in Grapevine

Project Update: Grubbs Volvo

We’re hard at work on Grubbs Volvo in Grapevine …

  • We’re erecting steel at the main building and plumbing rough-in is ongoing
  • Electrical undergound is continuing throughout the site
  • Rebar has been set in preparation to pour the Mezzanine slab
  • Sidewalks have been completed along Texan Trail
  • Grading is ongoing for the remaining paving

Thank you to our team and trade partners. We appreciate you!

Installing electrical underground throughout the site