Dallas

Exterior view of work being done on Emmanuel Chin Baptist Church in Lewisville, Texas

Project Update: Emmanuel Chin Baptist Church

We’ve completed the structural steel and metal deck, and are currently working on interior/exterior framing. Up next is the building dry-in which includes roofing and exterior wall finishes. Many thanks to our team and trade partners!

Exterior view of Jammy Inc's new warehouse, office and storage facility

Project Update: Jammy Inc in Fort Worth

We’re going vertical on Jammy Inc’s 50,000 SF building and have almost completed the exterior structure. We’ll start adding the roof sheeting and wall panels shortly, enclosing the building so we can begin interior work. Many thanks to our team and our trade partners.

Happy Thanksgiving

Happy Thanksgiving from all of us at Fort Construction. We would like to offer our sincere thanks to our wonderful clients, our dedicated employees, and our hard-working trade partners. Our office will be closed starting at 12pm today, Thursday and Friday. Enjoy the holiday!

View of steel framing at Holy Family Retreat Center in Fort Worth

Project Update: Holy Family Retreat Center

We are framing the Holy Family Retreat Center in Fort Worth. MEP rough in is starting and we’ll have the roof put on later this week. The chapel steel is up and we’re working on the light gauge framing now. Thank you team and trade partners – we appreciate your hard work.

Fort Construction President Scott Price

Happy 19th Anniversary, Scott!

The ultimate work anniversary. Scott Price, our fearless leader and President of Fort Construction, is celebrating 19 years! We appreciate his leadership, guidance and thoughtfulness. Thank you, Scott — let’s keep it going.

View of concrete for warehouse

Project Update: Jammy Inc

Concrete is poured for Jammy’s new 55,000 SF warehouse in Fort Worth! The site is located off Benbrook Highway and will include office space and storage. Thank you team and trade partners. We appreciate you.  

Exterior view of Ryder in Grand Prairie

Project Complete: Ryder in Grand Prairie

Ryder’s new facility in Grand Prairie is ready for move in! Our thanks to Ryder for the opportunity to work with them again. And we’re grateful to our team and trade partners for their hard work and dedication.

New Project: Holy Family Retreat Center

Fort Construction is the general contractor for the Holy Family Retreat Center in Fort Worth. This is a new build of a chapel and two-story retreat center along with site improvements. Dirt is being moved! We’ll keep you updated.  

Project Update: Denton CJDR

Interior drywall is complete and we’re getting ready to start painting at Denton Chrysler Jeep Dodge Ram. Appreciate the work by our team and trade partners 🙏🏼