Exterior Framing at Grubbs Volvo

Project Update: Grubbs Volvo

A quick look at what’s happening at Grubbs Volvo in Grapevine … Exterior framing at the showroom and service drive continues Completed decking installation at the shop, and started installing steel supports for RTU screens Prepped for a 600-yard concrete pour Electrical rough-in started at the main building Plumbing rough-in is ongoing throughout Our thanks

Project Update: Grubbs Volvo Read More »

Overhead view of Grubbs Volvo in Grapevine

Project Update: Grubbs Volvo

We’re hard at work on Grubbs Volvo in Grapevine … We’re erecting steel at the main building and plumbing rough-in is ongoing Electrical undergound is continuing throughout the site Rebar has been set in preparation to pour the Mezzanine slab Sidewalks have been completed along Texan Trail Grading is ongoing for the remaining paving Thank

Project Update: Grubbs Volvo Read More »