Project Update: CV Curtis Industrial
We’re about six weeks away from completion at CV Curtis Industrial Park. Thank you to our team and trade partners!
We’re about six weeks away from completion at CV Curtis Industrial Park. Thank you to our team and trade partners!
CV Curtis Industrial is looking terrific! We have storefronts on Buildings 1, 2 and 4. MEP rough in is ongoing in Buildings 1 and 2. We are installing the last roof which is on Building 3 and the remaining metal façade on Building 3. We are finishing up double siding sheetrock on Building 4. Thankful …
CV Curtis Industrial Park is underway! The project consists of four pre-engineered metal buildings. We erected red iron at Building 1 and poured the slab for Building 4. Great to see this project starting to take shape. We’ll keep you updated!