We’re hard at work on Grubbs Volvo in Grapevine …
- We’re erecting steel at the main building and plumbing rough-in is ongoing
- Electrical undergound is continuing throughout the site
- Rebar has been set in preparation to pour the Mezzanine slab
- Sidewalks have been completed along Texan Trail
- Grading is ongoing for the remaining paving